Knowledge Centre · Guide · Shoring cost

7 Ways to Reduce Shoring and Piled Foundation Costs

Shoring cost is usually set at the design desk, not on site. In this guide we describe seven ways to cut the cost of shoring and piled foundations without giving up safety, with examples from our own sites.

Mixed solution to reduce shoring cost: soil-nailed slope above and an anchored bored pile wall below in Küçükçekmece, 2023
Küçükçekmece, 2023 · soil-nailed slope above, anchored wall below

Topic

Shoring and foundation cost

Reading time

About 7 minutes

Written by

Abdullah Çetintaş, Geological Engineer

Updated

November 2026

Related services

Bored piles, anchors, soil nailing

Example

Küçükçekmece mixed shoring

Where does shoring cost come from?

First of all, a shoring system’s cost has several parts: pile quantities, anchors or props, the capping beam, shotcrete, monitoring and mobilisation. In addition, the excavation programme and how long the rig stays on site directly affect the total.

That is why the biggest saving lies before construction, at the design stage. After all, once you cast a pile, you cannot change its length or the number of piles.

How can shoring cost come down? 7 safe ways

1. A proper, sufficient site investigation

To begin with, shallow or incomplete boreholes force the designer to choose cautious parameters. As a result, piles and anchors come out longer than they need to be. By contrast, an investigation that goes deeper than the excavation and the piles often pays back more than it costs.

2. The right shoring system

Of course, not every excavation needs an anchored bored pile wall. For example, a cantilever wall in a shallow dig, or soil nailing in suitable ground, can cost far less. However, a neighbour close by or groundwater calls for a stiffer system.

3. Mixed solutions

Besides, you do not have to use the same system at every depth. In the deep excavation in Küçükçekmece, for instance, we used a soil-nailed slope in the upper part and an anchored bored pile wall below; in this way, we built an economical system that suited the ground at each depth.

4. Pile layout and diameter

In general, without groundwater, contiguous piles with shotcrete are usually enough. Secant piles, on the other hand, are only necessary to cut off water, because they need far more quantity.

5. Anchor rows and lengths

Similarly, the number of anchor rows, their spacing and their length set the quantity directly. So the designer sometimes finds a cheaper layout with fewer rows of higher-capacity anchors, or the reverse.

6. Using the wall in the permanent structure

Furthermore, shoring and foundations are usually separate designs, but they must fit together. For example, the pile wall can also serve as the outer formwork for the basement wall.

7. Programme and site layout

Above all, every day the rig stands idle costs money. Therefore, we plan the sequence with the excavation crew, the concrete logistics and the working platform before work starts.

Summary: what does each way save?

WayWhat it savesWatch out for
Sufficient site investigationShorter piles and anchorsBoreholes should go below the pile toes
The right systemAvoids needless stiffnessNeighbours and water decide
Mixed solutionA suitable system at each depthDesign the transition zone well
Contiguous pilesLess quantityOnly without groundwater
Optimised anchorsFewer anchor metresThe designer makes the call
Wall in the permanent structureSaves formwork and spaceMust fit the foundation design
ProgrammeRig and crew never waitDaily coordination with the excavation crew

What should never be cut when shoring cost comes down?

Indeed, some items look like savings but end up costing far more. For this reason, we never negotiate on the following.

  • Pouring through a tremie pipe in any bore that holds water or bentonite
  • Stressing and acceptance tests on anchors
  • A condition survey of adjacent buildings and monitoring throughout the excavation
  • Excavating in the stages set out in the design

We cover these points in detail in our guide to common site mistakes.

Frequently asked questions about shoring cost

We have collected the questions about shoring cost that we hear most often. However, if yours is not here, call us or write through the quote form.

Cost and proposals

What does shoring cost per square metre?

We do not publish a fixed price. That is because a shoring price is made up of pile metres, anchor metres, the capping beam, shotcrete and monitoring, and these change on every project.

Which shoring system is the cheapest?

In short, there is no single answer. For example, soil nailing is usually the most economical in suitable ground; however, a neighbour close by or groundwater calls for an anchored or secant pile wall.

Are internal props cheaper than anchors?

They can be in narrow, shallow excavations. On the other hand, in wide excavations props get in the way of digging and building; consequently, they can raise the total cost.

Who approves the changes you propose?

Always the designer. We prepare proposals with our design partner based on our site experience; however, the final decision belongs to the designer.

Abdullah Çetintaş, Geological Engineer, founder of Fen Zemin & İnşaat

Abdullah Çetintaş

Geological Engineer · Founder, Fen Zemin & İnşaat

In ground engineering and foundations since 2006. This guide draws on the site experience of Abdullah and our team.

LinkedIn profile · Last updated: November 2026

Let us review your shoring cost together

First, send us your site investigation and architectural drawings. Then let us look, together with our design partner, at whether a more economical shoring layout is possible.