Knowledge Centre · Field Notes · Piles under an existing building

Can Piles Be Added Under an Existing Building?

Yes, piles can be added under an existing building. However, we usually look at ground grouting first; piles come in where grouting is not enough. In both cases, the first step is to find out why the building is settling.

Micropiles, jet grout columns and grouting under an existing building: underpinning methods
Underpinning methods for an existing building, schematic drawing

Series

Your Questions

Topic

Underpinning

Methods

Grouting, micropiles, jet grouting

Written by

Abdullah Çetintaş

Published

November 2026

Reading time

About 5 minutes

Can you add piles under an existing building? The short answer

People search for this a lot, and we often hear it on the phone and on Instagram too. Most of those asking are owners who have seen cracks in their building or want to add a storey.

Short answer: piles can be added under an existing building. However, for an existing building we look at ground grouting first. If piles are needed, we usually use micropiles; these piles carry the load from the foundation down to firm ground.

First, find out why the building is settling

The most common mistake we see on site is applying a fix before finding the cause. For example, if a water leak is washing out the soil under the foundation, any work done before the leak is repaired is soon wasted.

That is why we start every job with a site visit, crack and settlement monitoring and a site investigation. Only then do we propose a method.

Why grouting first for an existing building?

Part of the settlement in existing buildings comes from voids under the foundation, loosened soil, or soil washed out by a water leak. Ground grouting fills these voids and densifies the soil.

In addition, grouting needs smaller drilling and pumping equipment than piling. That is why we consider grouting before piles for an existing building. If grouting is not enough, piles come in.

When are piles under an existing building needed?

A pile carries the building load through the weak soil down to a firm layer. On site, piles usually come up in these cases:

  • Settlement is still going on and the firm layer is deep
  • A storey is being added or the use is changing and the load will increase (adding a storey also needs legal permission)
  • An excavation on the neighbouring plot has affected the ground under the building
  • The site investigation shows a liquefaction risk

If piles are needed, we usually use micropiles. This is because bored pile rigs are large and heavy and cannot work inside a building or in a basement. Where the ground is loose sand or fill, jet grouting is also an option. The design sets the method after the structural review and the site investigation.

Which rigs do we use inside a building?

Inside a building and in basements we work with compact rigs that suit the ceiling height and the access; we hire these rigs for each job. Our own Casagrande C6 and Soilmec SM14, on the other hand, do not fit inside a building; we use them for anchors and micropiles outside the building.

That is why we always ask for the basement ceiling height and the width of the access at the quote stage. We then choose the rig to suit these dimensions.

Piles under an existing building and underpinning, step by step

  1. Survey: we inspect the cracks and settlement on site and set up monitoring points on the building.
  2. Site investigation: we have the site investigation carried out with our drilling partner.
  3. Structural review and design: with our design partner we assess the structural system and have the strengthening design prepared.
  4. Work in stages: we do not drill through the foundation everywhere at once; we carry out the grouting or the piles in the order set in the design.
  5. Connection to the foundation: if piles are used, we connect the new piles to the existing foundation with pile caps, beams or steel connections.
  6. Monitoring: we measure settlement during and after the work and show the result with records.

We explain the process in more detail on our underpinning page.

What drives the cost of piles under an existing building, and what do we need for a quote?

We do not give figures, because the condition of the building drives the cost: the chosen method and quantities, working conditions in the basement, work in stages, the site investigation and design, and the monitoring period. After the survey and the design, we give a quote based on quantities.

  • Architectural and structural drawings of the building, and the foundation plan if there is one
  • Photos of the cracks and problem areas
  • The site investigation and earlier assessments, if any
  • Basement ceiling height, access width and the address

If you have no drawings, write to us anyway. We will do a first survey and plan the investigation and design with our partners.

Questions about piles under an existing building

Short answers to the questions we hear most on this topic.

Owners and building managers

Does the building have to be emptied?

In most cases, no. We can work in the basement and around the building. However, the strengthening design makes this decision; if the building stays in use, we plan the sequence of work with the occupants.

Does foundation strengthening replace seismic retrofitting?

No. If the columns, beams and shear walls are weak, work on the foundation alone is not enough. If the building is classed as at risk, rebuilding and urban regeneration come into play.

Is every crack a foundation problem?

No. Cracks caused by settlement are usually diagonal and often start at the corners of doors and windows. A firm decision needs a site survey and a site investigation.

Abdullah Çetintaş, Geological Engineer, founder of Fen Zemin & İnşaat

Abdullah Çetintaş

Geological Engineer · Founder, Fen Zemin & İnşaat

In ground engineering and foundations since 2006. This note draws on the site experience of Abdullah and our team.

LinkedIn profile · Published: November 2026

Sources

Let us talk about your building

Send us the drawings of your building and photos of the cracks. Then we can define the problem together and plan the investigation and design needed.