Knowledge Centre · Guide · Protecting adjacent buildings

Protecting Adjacent Buildings in Deep Excavations

Protecting adjacent buildings is the most sensitive part of any basement excavation. In this guide we explain what puts neighbours at risk, how to choose the right shoring, which survey to carry out before work starts and how to monitor during the dig.

Protecting adjacent buildings in a deep excavation: multi-row anchored bored pile wall in Küçükçekmece, 2023
Küçükçekmece, 2023 · multi-row anchored wall

Topic

Deep excavations and adjacent buildings

Reading time

About 8 minutes

Written by

Abdullah Çetintaş, Geological Engineer

Updated

November 2026

Related services

Bored piles, anchors, jet grouting

Example

Küçükçekmece, 800 anchors

Why are adjacent buildings at risk in a deep excavation?

When you open an excavation, the soil at its edge loses lateral support. However strong the retaining wall is, it moves a little, and that movement reaches the foundations next door. Yet wall movement is not the only risk.

  • Wall movement: as the wall moves towards the excavation, the soil behind it settles.
  • Lowering the groundwater: as water drains away, soft layers compress and the neighbouring building can settle.
  • Ground loss during drilling: if an unsupported bore collapses, a void forms behind the wall.
  • Vibration and pressure: driven-pile vibration or uncontrolled jet grout pressure can cause damage.
  • Over-excavation: digging deeper than the design stage loads the wall all at once.

Which shoring works best for protecting adjacent buildings?

The closer and more sensitive the neighbouring building, the stiffer the wall must be. For this reason, excavation depth, ground, water and the depth of the neighbour’s foundation decide the system together.

SystemFor the neighbourWhen?
Cantilever pile wallMoves more at the topShallow excavation, firm ground
Anchored bored pile wallPrestress limits movementDeep excavation, neighbour close by
Propped wallStiff; no anchors under the neighbourNarrow excavation, or anchors not possible
Secant piles and jet groutingCuts off water, so less dewateringHigh groundwater
Soil-nailed wallWorks by movingAway from neighbours, suitable ground

In Küçükçekmece, for example, we used a bored pile wall with many rows of prestressed anchors in clay. In Karaköy, on the other hand, the groundwater led us to secant piles with a jet grout base.

A condition survey of the neighbouring building before excavation

Recording the condition of the neighbouring building before excavation protects both the neighbour and the project. After all, only that record can show whether a crack you notice later was already there.

  1. Photos and a signed record: we document the facade, the basement and existing cracks with dates.
  2. Foundation details: where possible, we find out the depth and type of the neighbour’s foundation.
  3. Monitoring points: we set up settlement and crack monitoring points before excavation.
  4. Baseline readings: we record starting values at every point.

Our advice: have the client, the contractor and the neighbour sign the survey together. That way, you head off disputes before they start.

Protecting adjacent buildings: measuring and monitoring

Monitoring shows whether the wall and the neighbouring building behave as the design predicts. In addition, if a movement approaches its limit, it buys you time to act.

MeasurementWhat it showsHow often?
Settlement pointsVertical movement of the neighbouring buildingRegularly, by excavation stage
Crack gaugesWhether existing cracks are openingThroughout the excavation
Wall-top surveyHorizontal movement of the wallAt every excavation stage
InclinometerWall movement with depthIf the design calls for it

The shoring design sets the frequency and the trigger values. On site, however, we also follow one rule of our own: we never dig to the next stage until the anchors in a row are stressed and locked off.

What should you do if a deep excavation opens next door?

As a neighbour, you can take steps too. In particular, a few steps at the start make it much easier to solve problems later.

  • Before the dig starts, have your building’s condition recorded with photos and a signed record.
  • Ask the contractor about the shoring system and whether the anchors will run under your building.
  • If you see a new crack during the excavation, take a dated photo.
  • Notify the contractor and the building inspection firm in writing straight away.

For legal matters, however, we recommend that you consult a lawyer. We cover the technical side: shoring, measurement and monitoring.

Protecting adjacent buildings: frequently asked questions

We have collected the questions about neighbouring buildings that we hear most often. However, if yours is not here, call us or write through the quote form.

Neighbours and clients

Which shoring system does the least harm to neighbours?

Usually a prestressed anchored or propped pile wall, because these systems limit wall movement. Even so, the ground, the water and the excavation depth decide the right choice together.

What happens if anchors run under the neighbouring plot?

The length and angle of an anchor can take it under the neighbouring plot. For this reason, settle the matter at the design stage and, if necessary, reach an agreement with the neighbour; for the legal side, consult a lawyer.

Do bored piles cause vibration?

We build bored piles by drilling, so vibration is low compared with driven piles. Still, the risk next to an adjoining building is not zero; that is why we recommend a survey and monitoring.

Does pumping groundwater affect the building next door?

It can, because soft layers compress as the water level drops. Therefore, in high groundwater, cutting off the water with secant piles and a jet grout base is often safer than pumping it.

How long does monitoring last?

Usually throughout the excavation and until the basement walls take the load. In the end, the shoring design and the readings decide the exact period.

Abdullah Çetintaş, Geological Engineer, founder of Fen Zemin & İnşaat

Abdullah Çetintaş

Geological Engineer · Founder, Fen Zemin & İnşaat

In ground engineering and foundations since 2006. This guide draws on the site experience of Abdullah and our team.

LinkedIn profile · Last updated: November 2026

A shoring and monitoring plan for your excavation

Send us your site investigation and design. Then let us agree the shoring system and the monitoring plan that protect the buildings around you.