Knowledge Centre · Tool · Pile concrete calculator

Pile Concrete Calculator: Drilling and Concrete Volume

Enter the diameter, length and number of piles in this pile concrete calculator to see total drilling and theoretical concrete volume at once. The same page also covers micropile grout and jet grout column volume. The results are for early budgeting, and the design sets the final quantities.

A pile concrete calculator example: concrete pour for secant bored piles in Karaköy, 2024
Karaköy, 2024 · bored pile concrete

Tool

Quantity and volume calculation

Methods

Bored, CFA, micropile, jet grout, DSM

Result

Theoretical geometric volume

Price

Only with your own unit rates

Prepared by

Abdullah Çetintaş, Geological Engineer

Updated

November 2026

Pile concrete calculator for bored and CFA piles

We use the same geometric calculation for bored piles and CFA piles. Enter the diameter in centimetres and the length in metres. You can also work out a rough budget with your own unit rates.

Total drilling800.0 m
Total rock drilling0 m
Theoretical concrete volume402.1 m³
Concrete per pile10.05 m³
Optional: rough budget with your own unit rates

Rough budget: —

Theoretical geometric volume. Concrete use on site is usually slightly higher. Reinforcement, mobilisation and taxes are not included.

Micropile grout calculator

Micropiles use cement grout instead of concrete. For this reason, the result appears as grout volume. However, grout take rises clearly depending on the ground.

Total drilling720.0 m
Total rock drilling0 m
Theoretical grout volume22.6 m³
Grout per pile0.38 m³
Optional: rough budget with your own unit rates

Rough budget: —

Theoretical geometric volume. Grout take on site is often clearly higher, depending on the ground. Steel, mobilisation and taxes are not included.

Jet grout and DSM column volume

For jet grout and DSM columns, the result is the geometric volume of treated soil. Cement use, on the other hand, depends on the soil and the mix design. For example, you need to deduct the overlap yourself for secant columns.

Total treated length1,000.0 m
Treated soil volume502.7 m³
Volume per column5.03 m³
Optional: rough budget with your own unit rates

Rough budget: —

Geometric volume of the columns. Binder take depends on the soil and the mix design; overlaps between columns are not deducted.

How does the pile concrete calculator work?

The calculation is a simple cylinder volume: V = π × D² / 4 × L. Here D is the pile diameter and L is the pile length. Then we multiply the result by the number of piles.

Pile diameterTheoretical concrete per metre
Ø60 cm0.283 m³/m
Ø80 cm0.503 m³/m
Ø100 cm0.785 m³/m
Ø120 cm1.131 m³/m
Ø150 cm1.767 m³/m
Ø200 cm3.142 m³/m

For example, 120 piles of Ø80 cm and 18 m length give 2,160 m of total drilling. The theoretical concrete volume then comes to about 1,086 m³.

What does the result leave out?

  • Concrete use on site is usually slightly higher than the theoretical volume.
  • Reinforcement, mobilisation and taxes are not included.
  • Pile head trimming, excavation and testing are separate items.
  • Temporary casing, rock drilling and site access change the price.

So the result does not replace a quote. Our bored pile cost guide explains the nine factors behind the price. For a firm figure, send your documents through the Request a Quote form.

Frequently asked questions about the pile concrete calculator

We have collected the questions we hear most often about this calculator. If yours is not here, however, call us or use the quote form.

Calculation and results

Why does a site use more concrete?

Because a borehole is not a perfect cylinder, and it widens in loose ground. In addition, we pour extra concrete at the pile head that we later trim.

Does the calculator give a price?

It only gives a rough budget from the unit rates you enter. We do not publish prices on the site, and we base our quotes on quantities.

What is the rock drilling field for?

It shows the length of pile in rock separately. That is because rock drilling has a different price from soil drilling.

Does the same calculation apply to CFA piles?

Yes, the geometric volume is the same. However, we usually do not use the rock drilling field for CFA piles.

Abdullah Çetintaş, Geological Engineer, founder of Fen Zemin & İnşaat

Abdullah Çetintaş

Geological Engineer · Founder, Fen Zemin & İnşaat

In ground engineering and foundations since 2006. This page draws on the site experience of Abdullah and our team.

LinkedIn profile · Last updated: November 2026

Request a quote based on your quantities

Send us the site investigation, the pile schedule and the drawings. Then we can prepare a quote based on measured quantities.